CBRM Pallet Village on track to welcome first residents in August
Construction is underway on the site and Pallet shelters are expected to arrive in late July
The 35 single-unit Pallet shelters for the CBRM Pallet Village are expected to arrive on-site the week of July 22, 2024. The Pallet shelters can each be assembled in under an hour.
It is estimated that it will take at least two to four weeks for power connections to each unit to be completed.
In the meantime, work is underway to convert one of the two former New Dawn Welding College buildings into an accessible community building for the Pallet Village. This building will include staff office spaces, washrooms and showers (including accessible washrooms and showers), laundry facilities, a shared kitchen and living room, and programming/clinical spaces (for physician, nursing, counselling, etc. meetings).